How to Analyze Project Budget Overruns in Excel

Subtract project_budget from project_actual for each project and sum the differences. Also show over-budget projects separately so savings do not conceal overruns. Net spending is 800 above budget. Gross overruns are larger because some projects are under budget.
By Better Analyst3 min read
On this page

Start with the sample data

This example uses synthetic business data in USD. Download the CSV and import it through Excel’s Data → From Text/CSV. Set dates to Date, amounts to Decimal Number, and identifiers to Text. The examples use Excel for Microsoft 365 on desktop with English formula names and comma separators.

Download the sample CSV · Data dictionary

Keep an untouched copy of the input. These are educational examples, not customer records or measured customer outcomes.

The result to check

Portfolio net budget overrun: 800 USD

Net spending is 800 above budget. Gross overruns are larger because some projects are under budget.

Build the analysis in Excel

1. Prepare the source and scope

Import operations.csv into a new worksheet with headers in row 1. Leave the source columns in their original order for the formulas below. Review the data dictionary before choosing the reporting period. Keep identifiers as text and convert numeric columns explicitly. Save a working copy so you can return to the original fixture.

2. Build the calculation

Subtract project_budget from project_actual for each project and sum the differences. Also show over-budget projects separately so savings do not conceal overruns.

=SUM(P2:P7)-SUM(O2:O7)

3. Reconcile and interpret the output

The expected check is portfolio net budget overrun: 800 USD. Net spending is 800 above budget. Gross overruns are larger because some projects are under budget. If your result differs, inspect the selected rows, data types and date filters before changing the formula.

4. Adapt the workflow to a recurring report

Replace the sample with a copy of your own source, retaining the same column meanings and units. Extend bounded ranges to include new rows, refresh PivotTables where used, and compare the result to an independent source total. Record the reporting period and any exclusions beside the output. Compare actuals to an approved budget version and distinguish committed costs from paid costs.

Checks before using your own data

  • Compare actuals to an approved budget version and distinguish committed costs from paid costs.
  • Keep blanks distinct from zero. Investigate missing records rather than hiding errors with a blanket IFERROR formula.
  • Verify results after changing filters, sorting rows or appending a new period. The sample output is a check for this fixture, not a forecast for your business.

Tools and reference guides

Continue with your own data

Analyze your spreadsheet

See the supported workflow and upload your file when you are ready. The sample is not loaded automatically.