NETWORKDAYS.INTL(start_date, end_date, [weekend], [holidays])One free generation or explanation per browser, shared across Excel and Google Sheets. Account usage limits apply afterward.
start_date:
The starting date from which to begin counting the number of working days.
end_date:
The ending date up to which to count the number of working days.
weekend:
(Optional) A string or number that specifies which days of the week are considered weekends. If omitted, the default is Saturday and Sunday.
holidays:
(Optional) A range or array of dates that should be considered as non-working days in addition to weekends.
The NETWORKDAYS.INTL function in Google Sheets is a useful tool for calculating the number of working days between two dates, while allowing for the specification of weekends and holidays. This function is particularly beneficial for project management, payroll calculations, and any scenario where understanding the number of business days is essential.
In simpler terms, NETWORKDAYS.INTL helps you determine how many weekdays fall between two dates, taking into account custom weekends and holidays.
Imagine you are managing a project timeline and need to calculate the number of working days between the project start and end dates:
| Task | Start Date | End Date |
|---|---|---|
| Task A | 2023-10-01 | 2023-10-10 |
| Task B | 2023-10-05 | 2023-10-15 |
You want to find out how many working days are available for each task, considering that your weekends are Saturday and Sunday.
To achieve this, you would use the NETWORKDAYS.INTL function as follows:
=NETWORKDAYS.INTL(B2, C2, 1)In this formula:
B2 is the cell containing the Start Date of the task.C2 is the cell containing the End Date of the task.1 indicates that Saturday and Sunday are considered weekends.When you apply the NETWORKDAYS.INTL formula to the Project Timeline, the output would look like this:
| Task | Start Date | End Date | Working Days |
|---|---|---|---|
| Task A | 2023-10-01 | 2023-10-10 | 7 |
| Task B | 2023-10-05 | 2023-10-15 | 8 |
In this case, Task A has 7 working days available, while Task B has 8 working days.
NETWORKDAYS.INTL is beneficial because it provides flexibility in defining weekends and allows for the inclusion of holidays. This makes it a powerful tool for accurately calculating working days in various business contexts. Additionally, it simplifies the process of managing project timelines and resource allocation.
NETWORKDAYS.INTL is an essential function for anyone managing timelines and schedules in Google Sheets, providing a reliable way to enhance project planning and execution.
Happy spreadsheeting!
You have a project timeline in a Google Sheet with start and end dates. Use NETWORKDAYS.INTL to calculate the number of working days between these dates, excluding weekends and holidays. This helps in accurate project planning and resource allocation.
Sign up for Better Analyst and get unlimited AI-powered formula generation, explanations, and advanced data analysis.
Browse our complete library of Google Sheets formula guides
Compare your options
Open a neutral research prompt in the AI tool you already use. Compare capabilities, limitations, and fit before you choose.
AI answers can be incomplete. Check source links, current pricing, and product documentation before deciding.